Which of the following outputs is most likely to result from a sprint retrospective?
A.
Stakeholder feedback
B.
Refined product backlog
C.
Product enhancement request
D.
Continuous improvement action
The Answer Is:
D
This question includes an explanation.
Explanation:
A sprint retrospective is a meeting held at the end of a sprint in Agile methodologies, where the team reflects on the past sprint to identify and agree on continuous improvement actions. The goal is to improve the process, teamwork, and methods used in the project. This may result in action items aimed at making the next sprint more efficient and productive. References: Schwaber, Ken, and Sutherland, Jeff. "The Scrum Guide".