Which of the following metrics is included in earned value management?
A.
The actual cost of scheduled work
B.
The actual cost of outstanding work
C.
The actual delay in project schedule
D.
The budgeted cost of work performed
The Answer Is:
D
This question includes an explanation.
Explanation:
Earned Value Management (EVM) includes several key metrics, one of which is the budgeted cost of work performed (BCWP). Here’s a detailed explanation:
Earned Value (EV): Represents the value of work actually performed in terms of the budget assigned for that work.
Planned Value (PV): The budgeted cost for the work planned/scheduled.
Actual Cost (AC): The actual cost incurred for the work performed.
Performance Measurement: BCWP is crucial for comparing planned work with actual progress and costs, helping in performance measurement and project forecasting.
References:
"Project Management: A Systems Approach to Planning, Scheduling, and Controlling" by Harold Kerzner.
PMI’s "A Guide to the Project Management Body of Knowledge (PMBOK Guide)".
CSQE PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"