ASQ CSQE Question Answer
Which of the following is an example of a poorly defined project milestone?
Program specification completed
Test plan approved by customer
Coding 50% completed
Program documentation approved
A milestone like "Coding 50% completed" is poorly defined because it is ambiguous and difficult to measure precisely. Here’s a detailed explanation:
Ambiguity: It is unclear what 50% completion means – is it 50% of total lines of code, 50% of modules, or 50% of functionality?
Measurement Challenges: Determining exact percentages of completion can be subjective and inconsistent.
Milestone Criteria: Good milestones should be clear, measurable, and verifiable. "Coding completed for module X" is more specific and measurable.
Project Tracking: Poorly defined milestones can lead to confusion and inaccurate tracking of project progress.
References:
"Software Project Management" by Bob Hughes, Mike Cotterell, and Rajib Mall.
"The Art of Project Management" by Scott Berkun.