A sprint started with 354 requirements.

A sprint started with 354 requirements. As the sprint progressed, 14 requirements were introduced, 6 requirements were removed, and 28 requirements were changed. What was the requirements volatility for this sprint?

A.

8.8%

B.

11.9%

C.

13.5%

D.

15.7%