Which of the following is an activity of Product Backlog management?
A.
Clearly expressing Product Backlog items
B.
Creating Sprint tasks
C.
Facilitating the Daily Scrum
D.
Planning the Sprint Backlog
The Answer Is:
A
This question includes an explanation.
Explanation:
Product Backlog management is primarily the responsibility of theProduct Owner. One of their key activities is toclearly express Product Backlog items, ensuring they are transparent and understandable for the Developers. This helps the Scrum Team deliver valuable Increments.
According to the2020 Scrum Guide, Product Backlog management includes:
Clearly expressing Product Backlog items.
Ordering the items to maximize value.
Ensuring the Product Backlog is transparent, visible, and understood.
Why the other options are incorrect:
B. Creating Sprint tasks:Sprint tasks are part of the Developers’ detailed planning during the Sprint and are not part of Product Backlog management.
C. Facilitating the Daily Scrum:This is a responsibility of the Developers, and the Scrum Master may only facilitate if explicitly requested.
D. Planning the Sprint Backlog:The Sprint Backlog is planned during Sprint Planning and is primarily the Developers' responsibility, not part of Product Backlog management.