CompTIA CS0-002 Question Answer
An organization has the following risk mitigation policies
• Risks without compensating controls will be mitigated first it the nsk value is greater than $50,000
• Other nsk mitigation will be pnontized based on risk value.
The following risks have been identified:
Which of the following is the ordei of priority for risk mitigation from highest to lowest?