Prior to asset operation, which of the following failure ranking techniques should be used?
A.
Design FMEA
B.
Breakdown FMEA
C.
Normal Wear Out FMEA
The Answer Is:
A
This question includes an explanation.
Explanation:
Design FMEA is correct because the phrase “prior to asset operation” places the analysis before the asset is in service. At that point, the organization is still trying to identify and reduce potential design-related failure modes before they become operational defects. Design FMEA evaluates how a product, system, equipment design, or component design might fail, what effects those failures could produce, and what controls or design changes should be applied before commissioning or operation. Breakdown FMEA is not the best answer because breakdown analysis is reactive and generally follows operational failure. Normal Wear Out FMEA is also not the correct term for pre-operation ranking; wear-out behavior is usually evaluated after understanding lifecycle degradation patterns and operating context. In CRL Reliability Engineering for Maintenance, the goal is to prevent defects from being installed into the asset base. ASQ defines FMEA as a systematic method to identify and prioritize possible failures in a design, process, product, or service, and it describes the tool as proactive—exactly why Design FMEA is the right pre-operation choice.
CRL PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"