The PRIMARY focus of an ongoing risk awareness program should be to:
A.
enable better risk-based decisions.
B.
define appropriate controls to mitigate risk.
C.
determine impact of risk scenarios.
D.
expand understanding of risk indicators.
The Answer Is:
A
This question includes an explanation.
Explanation:
The primary focus of an ongoing risk awareness program should be to enable better risk-based decisions, as this can help the organization to achieve its objectives, optimize its performance, and manage its risks effectively. An ongoing risk awareness program is a process of educating, communicating, and engaging the stakeholders about the organization’s risk management framework, methodology, and practices. An ongoing risk awareness program can help the stakeholders to understand the risk context, criteria, appetite, and profile of the organization, and to identify, assess, treat, monitor, and review the risks that may affect their roles and responsibilities. By doing so, an ongoing risk awareness program can empower the stakeholders to make informed and rational decisions that balance the benefits and costs of risk-taking, and that align with the organization’s strategy and goals.
[References:, •ISACA, Risk IT Framework, 2nd Edition, 2019, p. 761, •ISACA, Managing Human Risk Requires More Than Just Awareness Training2, , , , , , , , ]
CRISC PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"