Which of the following should be the PRIMARY recipient of reports showing theprogress of a...

Which of the following should be the PRIMARY recipient of reports showing the

progress of a current IT risk mitigation project?

A.

Senior management

B.

Project manager

C.

Project sponsor

D.

IT risk manager