Which of the following is MOST critical when designing controls?
A.
Involvement of internal audit
B.
Involvement of process owner
C.
Quantitative impact of the risk
D.
Identification of key risk indicators
The Answer Is:
B
This question includes an explanation.
Explanation:
The most critical factor when designing controls is the involvement of the process owner, who is the person responsible for the performance and outcomes of a business process. The process owner has the best knowledge and understanding of the process objectives, activities, inputs,outputs, resources, and risks. The process owner can provide valuable input and feedback on the design of controls that are relevant, effective, efficient, and aligned with the process goals. The process owner can also ensure that the controls are implemented, monitored, and improved as needed. The involvement of the process owner can also increase the acceptance and ownership of the controls by the process participants and stakeholders. The other options are less critical when designing controls. The involvement of internal audit can provide assurance and advice on the adequacy and effectiveness of the controls, but internal audit is not responsible for the design or implementation of the controls. The quantitative impact of the risk can help to prioritize and justify the controls, but it is not sufficient to determine the appropriate type and level of controls. The identification of key risk indicators can help to monitor and measure the risk and the performance of the controls, but it is not the main driver of the control design. References = Risk IT Framework, ISACA, 2022, p. 181
CRISC PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"