Following a business continuity planning exercise, an organization decides to accept an identified risk associated...

Following a business continuity planning exercise, an organization decides to accept an identified risk associated with a critical business system. Which of the following should be done next?

A.

Document the decision-making process and considerations used

B.

Perform a business impact analysis (BIA) to assess the impact of the risk

C.

Develop a disaster recovery plan (DRP) and business continuity plan (BCP) to ensure resiliency

D.

Develop a control to reduce the level of the risk