During the control evaluation phase of a risk assessment, it is noted that multiple controls...

During the control evaluation phase of a risk assessment, it is noted that multiple controls are ineffective. Which of the following should be the risk practitioner's FIRST course of action?

A.

Compare the residual risk to the current risk appetite.

B.

Recommend risk remediation of the ineffective controls.

C.

Implement key control indicators (KCIs).

D.

Escalate the control failures to senior management.