A risk practitioner has learned that the number of emergency change management tickets without subsequent...

A risk practitioner has learned that the number of emergency change management tickets without subsequent approval has doubled from the same period of the previous year. Which of the following is the MOST important action for the risk practitioner to take?

A.

Review the cause of the control failure.

B.

Temporarily suspend emergency changes.

C.

Recommend remedial training.

D.

Initiate a review of the change management process.