Which of the following tools can be used to communicate performance data in time sequence?
A.
Scatter diagram
B.
Pareto chart
C.
Control chart
D.
Flowchan
The Answer Is:
C
This question includes an explanation.
Explanation:
A control chart is used to communicate performance data in a time sequence. It displays data points over time, allowing for the analysis of trends, shifts, and variations in the process. This tool is effective for monitoring process stability and performance. Reference: "Statistical Quality Control" by Eugene L. Grant and Richard S. Leavenworth, which details the use of control charts in quality control processes.