Risk control includes making decisions using which of the following pieces of information?
A.
Acceptable levels of risk
B.
Fault tree analyses results
C.
Check sheet comparisons
D.
Analysis of experiments
The Answer Is:
A
This question includes an explanation.
Explanation:
Risk control involves making decisions using information about acceptable levels of risk. This process helps ensure that the risks associated with various activities are managed within tolerable limits, balancing the potential impact with the organization's risk appetite.
[Reference:, "Risk Management: Concepts and Guidance" by Carl L. Pritchard, ISO 31000: Risk Management guidelines, , ]