Which of the following tools is used for monitoring a capacity plan?
A.
Demonstrated capacity
B.
Resource planning
C.
Input/output control (I/O)
D.
Dispatch report &
The Answer Is:
C
This question includes an explanation.
Explanation:
Input/output control (I/O) is a type of tool that is used for monitoring a capacity plan. A capacity plan is a statement of the resources needed to meet the production plan over a medium-term horizon. A capacity plan can be stated in different units of measure depending on the type of manufacturing environment, such as hours, units, tons, or dollars. Input/output control (I/O) is a method of measuring and comparing the actual input and output of a work center or a production line against the planned input and output. Input is the amount of work that is released to the work center or the production line, and output is the amount of work that is completed by the work center or the production line. Input/output control (I/O) helps to monitor the performance and efficiency of the work center or the production line, and to identify any deviations or problems that may affect the capacity plan. Input/output control (I/O) also helps to adjust the input or output levels as necessary to maintain the balance between demand and supply, and to achieve the desired throughput.
References: CPIM Exam Content Manual Version 7.0, Domain 6: Plan, Manage, and Execute Detailed Schedules, Section 6.3: Monitor Detailed Schedules, Subsection 6.3.2: Describe how to monitor input/output control (I/O) (page 60).
CPIM-Part-2 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"