Establishment of goals and baselines prior to entering the plan-do-check-act (FDCA) cycle allows improvement teams...

Establishment of goals and baselines prior to entering the plan-do-check-act (FDCA) cycle allows improvement teams to:

A.

determine whether an effective change was made in the process.

B.

determine if improvement potential is complete.

C.

assure successful completion of the improvement effort.

D.

complete the project with fewer iterations.