When the discrete available-to-promise (ATP) method is used, the master production receipt quantity is committed...

When the discrete available-to-promise (ATP) method is used, the master production receipt quantity is committed to:

A.

any request for shipment prior to the planning time fence.

B.

any request for shipment prior to the demand time fence (DTF).

C.

requests only for shipment before the next master production schedule (MPS) receipt.

D.

requests only for shipment in the period of the receipt.