The primary reason for tracing a component with scheduling problems to Its master production schedule (MPS) item is to:

A.

revise the rough-cut capacity plan.

B.

reschedule a related component on the shop floor.

C.

check the accuracy of the bills for the MPS items.

D.

determine if a customer order will be impacted.