Which of the following is the MOST important consideration in a full-scale disaster recovery test?

Which of the following is the MOST important consideration in a full-scale disaster recovery test?

A.

Sign off by the Chief Information Officer (CIO)

B.

Financial cost of the organization

C.

Business interruption

D.

Available Information Technology (IT) hardware