A manufacturer has a primary assembly line supported by output from several subassembly lines.

A manufacturer has a primary assembly line supported by output from several subassembly lines. Which of the following scenarios would be the best argument for a multilevel master scheduling process?

A.

Low variation in aggregate subassembly demand

B.

High variation in aggregate subassembly demand

C.

Low variation in subassembly demand mix

D.

High variation in subassembly demand mix