APICS CPIM-8.0 Question Answer
A healthcare organization is preparing an exercise test plan of its Disaster Recovery Plan (DRP) for the Electronic Medical Record (EMR) application. The Business Continuity (BC) analyst is reviewing the requirements of the DRP. The EMR must provide basic charting services within 4 hours, must not lose more than 15 minutes of data, and must be fully functional within 12 hours. At the completion of the exercise, the analyst is preparing a lessons learned report and notes that the EMR was available after 3 hours and 25 minutes of data was lost. Which PRIMARY requirement needs to be addressed because of the exercise?