A company assembles kits of hand tools after receipt of the order from distributors and uses two-level master scheduling. The appropriate levels of detail for the forecasts that are input to master scheduling would be total number of kits and:

A.

each unique tool.

B.

percentage of total for each tool.

C.

raw material requirements.

D.

specific kit configurations.