A quality Improvement team has Identified specific changes to Implement for a quality Improvement Initiative. As the next step, the team would like to establish a concrete timeline for implementation. Which of the following is the best tool to use for this step?

A.

process map

B.

Gantt chart

C.

Ishikawa diagram

D.

bar graph