At what point in the development of a category strategy should spend review occur?
A.
After key internal stakeholders agree on sourcing priorities
B.
After development of the sourcing team
C.
After presentation of the strategy to senior management
D.
During validation of the savings or contribution
The Answer Is:
D
This question includes an explanation.
Explanation:
Category Strategy Development: Involves analyzing spend, defining sourcing priorities, and forming a strategy.
Spend Review: Critical to understand current expenditures and identify savings opportunities.
Timing: Conducting spend review during the validation phase ensures that the projected savings or contributions are realistic and achievable.
Validation Phase: This phase involves confirming that the strategic approach will deliver the expected benefits.
Sequence: Conducting spend review after stakeholder agreement, team development, or strategy presentation might miss critical insights needed for validation.
Conclusion: Spend review should occur during the validation of the savings or contribution to ensure the strategy is grounded in accurate financial analysis.
References
Category Management in Purchasing by Jonathan O'Brien.
The Procurement and Supply Manager's Desk Reference by Fred Sollish and John Semanik.
CIPS Category Management Guide.
CORE PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"