ISM CORE Question Answer
A sourcing manager is evaluating the following bids:
Quality ScoreCost
Supplier 190$100,000
Supplier 290$104,000
Supplier 3100$105,000
Supplier 4100$110,000
To score the cost attribute, the company with the lowest cost is awarded 100 points. The remaining companies lose 1 point for every 1% in higher costs. The overall weighting for the score is 50% quality and 50% cost.
Which supplier should be awarded the contract?