ISM CORE Question Answer
A company buys 200 metric tons of ethylene per month. The firm has a one-year agreement with Supplier X to buy the ethylene at $1000 per metric ton. After 3 months, the market price drops to $900 per metric ton, and the firm renegotiates the price to $890 per metric ton for the remaining contract term.
What savings should be reported?