During the design phase, the CM should perform which of the following tasks?

During the design phase, the CM should perform which of the following tasks?

A.

Review contract milestones, payment procedures, and communication procedures.

B.

Review cost estimate, schematic design, and scheduling conferences with regulatory agencies.

C.

Review staffing assignments, labor affidavits, and historical trust.

D.

Review plans, final Right-of-Way (ROW) documents, and as-built submittals.