Winter Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

During the design phase, the CM should perform which of the following tasks?

During the design phase, the CM should perform which of the following tasks?

A.

Review contract milestones, payment procedures, and communication procedures.

B.

Review cost estimate, schematic design, and scheduling conferences with regulatory agencies.

C.

Review staffing assignments, labor affidavits, and historical trust.

D.

Review plans, final Right-of-Way (ROW) documents, and as-built submittals.

Construction-Manager PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now Construction-Manager pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"