An agency CM is assigned to a new construction project using the CMAA A-2 Standard...

An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?

A.

The owner should plan for delayed completion.

B.

Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.

C.

The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.

D.

The owner should charge the contractor daily liquidated damages.

Construction-Manager PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now Construction-Manager pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"