CMAA Construction-Manager Question Answer
An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?