An assessment of the gaps in capability should result in a list of:
A.
Performance measures.
B.
Unmitigated residual risks.
C.
Implementation costs.
D.
Potential improvements.
The Answer Is:
D
This question includes an explanation.
Explanation:
The COBIT 2019 Design Guide explains:
"The outcome of assessing current capability versus target capability is the identification of capability gaps. These gaps indicate areas for potential improvement and feed directly into the planning and implementation stages."
Hence, the result of such an assessment is a list ofpotential improvements.