Perform a risk analysis to determine the expected profit or (loss) from a project which has four possible disjoint outcomes:
Outcome A shows a profit of $340,000 and has a probability of 0.25.
Outcome B shows a profit of $120,000 and has a probability of 0.40.
Outcome C shows a loss of $40,000 and has a probability of 0.10.
Outcome D shows a profit of $100,000 and has a probability of 0.25.