How do you set a freestyle project to be parameterized?

How do you set a freestyle project to be parameterized?

A.

From "Project Configuration," select "This project is parameterized."

B.

Freestyle projects don't accept parameters

C.

Choose the project from the parameterized list in the "Configure System" section.

D.

All freestyle projects are parameterized