A daily monitoring report reveals that an IT employee made a change to a firewall...

A daily monitoring report reveals that an IT employee made a change to a firewall rule outside of the change control process. The information security manager's FIRST step in addressing the issue should be to:

A.

require that the change be reversed

B.

review the change management process

C.

perform an analysis of the change

D.

report the event to senior management