Which of the following would BEST determine whether a post-implementation review (PIR) performed by the...

Which of the following would BEST determine whether a post-implementation review (PIR) performed by the project management office (PMO) was effective?

A.

Lessons learned were implemented.

B.

Management approved the PIR report.

C.

The review was performed by an external provider.

D.

Project outcomes have been realized.