Management receives information indicating a high level of risk associated with potential flooding near the...

Management receives information indicating a high level of risk associated with potential flooding near the organization's data center within the next few years. As a result, a decision has been made to move data center operations to another facility on higher ground. Which approach has been adopted?

A.

Risk avoidance

B.

Risk transfer

C.

Risk acceptance

D.

Risk reduction