An IS auditor learns that an in-house system development life cycle (SDLC) project has not...

An IS auditor learns that an in-house system development life cycle (SDLC) project has not met user specifications. The auditor should FIRST examine requirements from which of the following phases?

A.

Configuration phase

B.

User training phase

C.

Quality assurance (QA) phase

D.

Development phase