An IS auditor is reviewing documentation of application systems change control and identifies several patches...

An IS auditor is reviewing documentation of application systems change control and identifies several patches that were not tested before being put into production. Which of the following is the MOST significant risk from this situation?

A.

Loss of application support

B.

Lack of system integrity

C.

Outdated system documentation

D.

Developer access 1o production