A new system development project is running late against a critical implementation deadline.

A new system development project is running late against a critical implementation deadline. Which of the following is the MOST important activity?

A.

Ensure that code has been reviewed.

B.

Perform user acceptance testing (UAT).

C.

Document last-minute enhancements.

D.

Perform a pre-implementation audit.