If an it_project_manager does not want to equally distribute hours across the resource plan time...

If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?

A.

Even.

B.

Any.

C.

Back Load.

D.

Front Load.