To minimize the number of change orders, it is best to have
A.
complete plans and specifications.
B.
a builder's insurance policy and performance bond.
C.
multiple prequalified bidders.
D.
a qualified construction manager and subcontractors.
The Answer Is:
A
This question includes an explanation.
Explanation:
The primary cause of change orders is incomplete or unclear plans and specifications. Ensuring that drawings and specs are fully developed before bidding reduces ambiguity, scope gaps, and the likelihood of modifications during construction.
A (Correct): Complete plans/specs = fewer change orders.
B: Bonds/policies protect financially but do not reduce change orders.
C: Prequalification ensures capable bidders but doesn’t eliminate scope issues.
D: Competent managers/subcontractors help but cannot offset incomplete design docs.
[Reference: CHFM Handbook – Planning, Design, and Construction domain., , ===========, ]
CHFM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"