Which of the following is the BEST method to confirm whether a pilot project was successful?

A.

Determine whether the pilot aligns with the as-is enterprise architecture (EA).

B.

Evaluate whether the pilot project achieved planned schedule and cost.

C.

Assess the results of the pilot project against the expected performance outcomes.

D.

Review the metrics recorded in the IT balanced scorecard.