An enterprise has a large backlog of IT projects.

An enterprise has a large backlog of IT projects. The current strategy is to execute projects as they are submitted, but executive management does not believe this method is optimal. Which of the following is the MOST important action to address this concern?

A.

Implement stage-gating to determine the value of each project.

B.

Establish a performance dashboard that determines business value.

C.

Implement a methodology to prioritize projects based on resource availability.

D.

Create a combined business/IT committee to determine project prioritization.