When is the BEST time for a facility manager to offer suggestions on a project at minimal cost?
Upon completion of the project
Throughout the project
Early in the design development process
After the drawings and prices are finalized
The IFMA Project Management competency stresses that early-stage input minimizes costs and maximizes impact.
Early design input (C) allows facility managers to influence layout, materials, and costs before finalization.
Throughout the project (B) may be too late for cost-effective changes.
Post-completion (A) and finalized pricing (D) lead to costly rework or delays.
Engaging early ensures efficient space utilization, energy efficiency, and long-term cost savings.