A project sponsor indicates that a project should build a facility at the lowest cost,...

A project sponsor indicates that a project should build a facility at the lowest cost, in the least time, and with the highest quality. What should the project manager do?

A.

Work with the sponsor to refine the project charter with more feasible constraints

B.

Implement the project with the given constraints, as instructed by the project sponsor

C.

Inform the project sponsor that a lower-quality project will be provided

D.

Inform the project sponsor that the project cannot proceed with the given constraints