Under the design-bid-build project delivery, what is the next step after the procurement phase has...

Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?

A.

The contractor begins negotiating agreements with subcontractors.

B.

The owner forwards construction contract agreements to subcontractors.

C.

The contractor and owner issue an amendment indicating the project is in the construction phase.

D.

The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.