Within CSI’s project delivery framework, the Design stage (which includes schematic design and design development) is where the architect/engineer (A/E) works with the owner to evaluate options, select specific systems, and record decisions that will later be fully detailed in the construction documents.
CSI’s project-phase descriptions (as presented in the CSI Project Delivery Practice Guide and CDT study materials) explain the stages roughly as follows (paraphrased, not verbatim):
Project Conception: The owner defines a need or opportunity, explores whether a project is warranted, and considers general feasibility. The focus is on defining the reason for the project, not picking specific products or systems.
Programming: The owner’s requirements and objectives are documented—space needs, performance criteria, budget, schedule, and qualitative expectations. At this point, needs and performance requirements for systems (e.g., “energy-efficient HVAC,” “durable flooring”) are identified, but not necessarily specific named products or system configurations.
Design:
Schematic Design: General design concepts, overall configuration, and preliminary system approaches are developed; the owner begins making more concrete decisions.
Design Development: The A/E and consultants refine and confirm decisions about specific systems, materials, and assemblies, and these decisions are documented so they can be incorporated into specifications and drawings.
Construction Documents: The A/E takes those already-made decisions and fully documents them in coordinated drawings and specifications, but this phase is not usually where the majority of decisions about which specific products and systems to use are first obtained; instead, it formalizes and details what was already decided in Design.
CSI’s CDT content emphasizes that during Design Development, the A/E “confirms and documents owner decisions about materials, products, and systems” so that these can be translated into clear contract documents during the Construction Documents phase. That activity—obtaining and documenting the owner’s decisions about specific products and systems—is core to the Design stage, making Option B correct.
Why the other options are not correct under CSI’s framework:
A. Construction documentationIn the Construction Documents phase, the A/E develops the detailed drawings and specifications based on decisions made earlier. Changes and additional decisions can occur here, but CSI treats the primary “obtaining and documenting owner choices” as a Design-stage responsibility; the CD phase is about formalizing and coordinating them into contract documents.
C. Project conceptionAt conception, there often isn’t an A/E contracted yet, and the owner is still deciding whether to proceed at all. Product and system decisions would be far too early and poorly defined at this point.
D. ProgrammingProgramming focuses on what the facility must do, not on exactly how via specific products or named systems. It defines performance and functional requirements (e.g., acoustical needs, energy performance) but typically stops short of selecting specific manufacturers or detailed system configurations.
Key CSI-aligned references (no links):
CSI Project Delivery Practice Guide – chapters on project phases (Programming, Design, Construction Documents) and owner/A/E responsibilities.
CSI CDT Body of Knowledge – sections on the Design phase and decision-making responsibilities for products and systems.