During the project closeout phase, what is an appropriate task for the facility manager?

During the project closeout phase, what is an appropriate task for the facility manager?

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents