As a project manager representing a private client, which of the following instances would best...

As a project manager representing a private client, which of the following instances would best benefit from a constructability review meeting?

A.

The client is unfamiliar with this type of project.

B.

The project team consists of multiple new members.

C.

The site presents unusual challenges and constraints.

D.

The contractor is unable to commit to original schedule.