The decision whether risk treatment needs to take place
B.
The report advising the board of management to accept all identified risks
C.
The list of all identified risks
D.
The required budget treating the data center risk
The Answer Is:
A
This question includes an explanation.
Explanation:
In the EPI framework for risk management, after the risk identification and risk analysis steps, therisk evaluationstep determines whether the assessed risks areacceptableorrequire treatmentbased on the organization’s risk appetite, criteria, and the potential impact. The evaluation leads to a decision on whether risk treatment needs to take place.
It isnotsimply compiling all risks (so option C is incorrect).
It isnotexclusively about budgeting (so option D is incorrect) though budgeting follows treatment decisions.
It isnotnecessarily advising to accept all risks (so option B is incorrect) but rather it supports decision-making on treatment.
Therefore, option A is correct: the outcome is the decision whether to treat the risk.
EPI DCFOM-Aligned Reference Concepts
Risk evaluation assesses identified and analysed risks against risk criteria to decide on acceptability or need for treatment.
The outcome is a documented decision-making step in the risk management process.
CDFOM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"