Exin CDCS Question Answer
Management requests a 15-minute battery bank at full UPS load. UPS specs:
30 kVA, PF 0.8
Battery 384 V (192 cells), end discharge 308 V
Inverter PF 0.8, 400 V output
What information is missing to perform the calculation?